Court of AppealDismissedCivil Appeal No. 339 of 2012

Karuri Civil Engineering (K) Limited v Equity Bank Limited [2019] KECA 866 (KLR)

Court of Appeal
8 March 2019
5,268 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~21 min to read original · ~4 min brief

The bottom line

#

A Kenyan construction company lost its bid to recover Ksh. 75 million from Equity Bank because its equipment detention was caused by its own contract non-performance, not the bank's delayed payment.

What this practically means

#

Executive summary

#
The appellant, a construction company, contracted with the Office of the President to rehabilitate a sewerage system for the Department of Defence. Equity Bank issued a performance bond of Ksh. 5,735,647.70 and, separately, an Advance Payment Bond. After the contract was terminated in July 2004, the Bank paid the bond sum only on 23rd September 2008, some four years later. The appellant sued for special damages of Ksh. 75,285,000/= for loss of user of its plant, machinery and equipment, which it said were detained because of the delayed payment. Havelock J dismissed both the claim and the Bank's counterclaim for reimbursement. On first appeal, the Court of Appeal reaffirmed that the doctrine of privity of contract cannot oust responsibility to a third party beneficiary of a performance bond, since the Bank issued the bond at the appellant's request and charged a 2% premium. The court corrected the trial judge on one point: the performance bond and the advance payment bond, though contractually separate, are interlinked and share the same trigger for demand. Nevertheless, the appeal failed on causation. Evidence showed the detention of the equipment was a consequence of the appellant's own non-performance of the contract and of non-payment of the balance of the Advance Payment Guarantee, not of the delayed payment of the performance bond; the bond made no mention of the equipment and was not an insurance cover for the appellant. The appeal was dismissed, the dismissal of the counterclaim was affirmed (there being no cross-appeal), and each party was ordered to bear its own costs.

Questions the Court framed

#

The issues the Court set itself to decide, in its own words.

  1. 1.Whether the judgment of the trial court was contradictory in finding the respondent could not rely on privity of contract yet dismissing the claim
  2. 2.Whether the performance bond and the advance payment bond were separate and distinct
  3. 3.Whether the respondent Bank was liable to the appellant for special damages for loss of user of detained plant, machinery and equipment on account of delayed payment of the performance bond
  4. 4.Whether the detention of the appellant's equipment was causally linked to the delayed payment of the performance bond

Key legal issues

#
01

Privity of contract and the right of a third party beneficiary to sue on a performance bond

Holding

The appellant, as the third party beneficiary at whose request the bond was issued and for whose benefit the premium was charged, had locus standi to sue on the bond; the privity defence fails.

Reasoning

The Bank issued the bond on the appellant's application, received a 2% premium as consideration, and the trigger for enforcement was non-performance of the appellant's contract. Following Gakombe and the collateral contract exception in Shanklin Pier, and the exceptions recognised in Aineah Likuyani Njirah, the court reaffirmed that privity cannot shield a guarantor from a third party beneficiary of a performance bond.

p. 4
02

Whether the trial judgment was contradictory

Holding

No. The trial court correctly analysed privity in two parts - locus standi first, then proof of liability - and the appellant misapprehended this approach.

Reasoning

Liability under a performance bond is a question of both fact and law. Having conferred locus standi, the court was still required to determine whether the appellant proved special damages for loss of user. It found liability unproved. The two-stage reasoning was coherent, not contradictory.

p. 5
03

Relationship between performance bond and advance payment bond

Holding

The trial court erred in holding the two bonds separate and distinct; they are interlinked, founded on the same contract, with distinct purposes but the same trigger for demand.

Reasoning

Applying Caterpillar Motoren, the court held that although the bonds are contractually separate, they both arise from the same underlying contract and non-performance triggers demand under either. However, this error did not avail the appellant because the delayed payment of the performance bond was still not the cause of the detention of the equipment.

p. 5
04

Causation and liability for loss of user of detained equipment

Holding

The respondent Bank was not liable; the detention was caused by the appellant's own non-performance of the contract, and the bond did not cover or mention the equipment.

Reasoning

The evidence of PW2 and PW4 showed the equipment was held by the Department of Defence due to non-payment of the balance of the Advance Payment Guarantee and the appellant's non-performance. The decision to detain was made by the Department of Defence, not the Bank. Loss lies where it falls; the only remedy for delayed payment would be interest accruing to the Department of Defence as beneficiary, and the bond was not an insurance cover for the appellant.

p. 6

Legal principles established

#
  • The doctrine of privity of contract cannot be used to oust responsibility to a third party beneficiary of a performance bond
  • An 'on demand' performance bond creates primary, independent liability payable on demand, not dependent on default under the principal contract
  • A performance bond and an advance payment bond, though contractually separate, are interlinked and founded on the same contract; their purposes are distinct but the trigger for demand is the same

Court orders

#
  1. 1.The appeal is dismissed
  2. 2.The decision of the trial court dismissing the counterclaim is affirmed (there being no cross-appeal)
  3. 3.Each party to bear its own costs in this appeal

The bench

#

One judgment of the whole court — no separate or dissenting opinions.

William Ouko
W. OukoJA
Currently serving
majority
majority
majority
On appeal from
High Court of Kenya at Nairobi
Nairobi HCCC No. 694 of 2008
Jurisdiction invoked
First appeal to the Court of Appeal under the Court of Appeal's appellate jurisdiction (no specific provision stated in the judgment)

Relief refused

#

Special damages of Ksh. 75,285,000/= for loss of user and detention of plant, machinery and equipment

The detention of the equipment was caused by the appellant's own non-performance of the contract, not by the Bank's delayed payment of the bond; the bond neither mentioned nor covered the equipment

p. 6

A finding that the trial court's judgment was contradictory

The trial court took a two-pronged approach: first determining locus standi on privity, then evaluating whether liability and damages were proved

p. 5

Costs

Each party is to bear its own costs in this appeal.

Quotable passages

#

Verbatim from the judgment, each located to the page it appears on in the official PDF — so these can be cited and checked directly.

In our considered view, the doctrine of privity of contract cannot be used to oust responsibility to a third party beneficiary of a performance bond.
p. 4Privity of contract - third party beneficiary of a performance bond
The bonds are contractually separate; however, it is the purpose of the bonds that are distinct; the trigger for demand for payment is the same namely non-performance of the contracted works.
p. 5Relationship between performance bond and advance payment bond
Detention was a direct consequence of non-performance; neither delayed payment of the bond nor the advance payment guarantee were causes of retention or detention of the appellant's equipment.
p. 6Causation - detention of equipment
For the various reasons stated above, we find this appeal has no merit and is hereby dismissed. There is no cross-appeal on dismissal of the counterclaim and we affirm the decision of the trial court in dismissing the counterclaim. Each party is to bear its own costs in this appeal.
p. 6Final orders - dismissal, affirmation of trial court, costs

Key timeline

#

Practical implications

#

Frequently asked questions

#

Later judgments citing this (2)

#

Judgments in the corpus that rely on this one. Where the Court said how it treated the authority, that is shown.

Cite this brief

#

Cite this brief

Caselaw, "Karuri Civil Engineering (K) Limited v Equity Bank Limited [2019] KECA 866 (KLR)", Case Analysis (2019). Civil Appeal No. 339 of 2012. Source: https://new.kenyalaw.org/akn/ke/judgment/keca/2019/866/eng@2019-03-08

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.