The bottom line

#

Kenya's Court of Appeal upheld an arbitral award against Trishcon Construction, confirming that parties who consent to arbitration and participate after deadlines cannot later challenge the outcome.

What this practically means

#

Executive summary

#
The Court of Appeal (Githinji, Sichale and Otieno-Odek JJA) dismissed both the appeal and the cross-appeal against a High Court ruling by Muga Apondi, J. that had refused to set aside an arbitral award in a construction dispute over 32 apartments on LR No. 330/274, Lavington. The appellant, Trishcon Construction Company Limited, argued that the arbitration was conducted pursuant to a court order under Order 45 of the Civil Procedure Rules rather than the Arbitration Act, that the arbitrator wrongly enjoined the 2nd respondent as a party and exceeded his mandate by awarding damages for breach of contract, that the award was a nullity for being filed outside the extended 120-day period, that the arbitrator misconducted himself by secretly publishing the award, and that the trial judge's 14-month delay in delivering the ruling occasioned injustice. The Court held that the consent order of 24th April 2007 marked the suit settled and transferred disputes to arbitration by consent, so the trial court ceased to be seized of the matter and Order 45 was inapplicable. It further held that the consent order itself made Mr. Dhanji Velji party to the arbitration, with estoppel operating against the appellant for failing to appeal the dismissal of its joinder challenge; that the arbitrator's mandate is fixed by contract and the court cannot rewrite it absent proved coercion, fraud or undue influence; and that arbitral jurisdiction is consensual, so active participation after lapse of the extended timeline amounted to acquiescence. The delay ground also failed, the appellant having proved no miscarriage of justice. This judgment binds lower courts on the consensual character of arbitral jurisdiction and mandate.

Questions the Court framed

#

The issues the Court set itself to decide, in its own words.

  1. 1.Whether the arbitration proceedings were conducted under the Arbitration Act or under Order 45 of the Civil Procedure Rules, and whether the judge erred in treating the matter as governed by the Arbitration Act
  2. 2.Whether the arbitrator erred in enjoining the 2nd respondent, Mr. Dhanji Velji, as a party to the arbitration proceedings
  3. 3.Whether the arbitrator exceeded the scope of his mandate by awarding damages for breach of contract beyond the valuation contemplated in the consent order
  4. 4.Whether the alleged secret publication of the award amounted to arbitrator misconduct justifying setting aside the award
  5. 5.Whether the arbitrator's failure to file the award within the extended 120-day period rendered the award a nullity
  6. 6.Whether the judge erred in failing to apply Nyangau vs. Nyakwara and in applying Kihuni vs. Gakunya
  7. 7.Whether the judge's delay of fourteen months in delivering the ruling rendered it a nullity or occasioned a miscarriage of justice

Key legal issues

#
01

Governing framework of the arbitration: Arbitration Act vs Order 45 Civil Procedure Rules

Holding

The arbitration was conducted by consent under the Arbitration Act; Order 45 was inapplicable.

Reasoning

The consent order of 24th April 2007 marked the suit settled and referred any dispute on inspection and valuation to arbitration. Kimaru, J. enforced that arbitration clause. Once the suit was marked settled, the trial court ceased to be seized of the dispute, so there was no pending substantive matter over which Order 45 could operate. Both parties persistently invoked the Arbitration Act in their submissions, confirming the governing framework.

p. 5
02

Joinder of the 2nd respondent to the arbitration

Holding

The arbitrator did not err in enjoining Mr. Dhanji Velji; the consent order itself made him a party, and the appellant's failure to appeal the dismissal of its challenge to the joinder raised an estoppel.

Reasoning

Paragraphs 3 and 4 of the consent order referred to disputes between Mr. Dhanji and Mr. Mohammed Salim Shamshudin, making the 2nd respondent pivotal to the reference. Further, the appellant had challenged the joinder in Miscellaneous Application No. 598 of 2008, which was dismissed and never appealed, conclusively determining the issue.

p. 5
03

Whether the arbitrator exceeded his mandate

Holding

The arbitrator acted within his mandate; the parties affirmed the pleadings on oath as the basis of the claims, and no coercion, fraud or undue influence was proved.

Reasoning

The mandate is fixed by the consent order. The parties confirmed on oath before the arbitrator that the pleadings filed were the basis of each party's claim. The court cannot rewrite the contract; citing National Bank of Kenya v Pipeplastic and Alghussein v Eton College, the appellant could not take advantage of its own position to defeat the award.

p. 5
04

Whether lapse of the 120-day period rendered the award a nullity

Holding

No: the parties extended the timeline by consent, actively participated after the lapse, and no party intimated that time was of the essence; acquiescence extended the arbitrator's timeline.

Reasoning

Unlike court jurisdiction, arbitral jurisdiction is conferred by consent of the parties. The parties extended time from 45 to 120 days and continued participating after the lapse. No prejudice was shown and no party asserted at the earliest opportunity that time was of the essence, so technicality cannot defeat the cause of justice.

p. 6
05

Effect of the judge's 14-month delay in delivering the ruling

Holding

Delay does not automatically nullify a judgment; the appellant failed to prove the delay occasioned a miscarriage of justice or erroneous findings of fact.

Reasoning

Relying on Bond v Dunster Properties, Cobham v Frett and Kenyan decisions, findings of fact are not set aside merely because judgment was seriously delayed; the test is whether the judge was plainly wrong or his recollection of the evidence was at fault on a material point. The appellant offered only bare allegations without proof.

p. 7
06

Alleged misconduct in secretly publishing the award

Holding

Releasing the award to a party who pays outstanding arbitration fees is an accepted practice and does not amount to misconduct warranting setting aside the award.

Reasoning

The trial judge found it is accepted practice that if one party does not pay its share of fees, the other may pay the full fees and collect the award. In any event, Order 45 was inapplicable, so alleged non-compliance with its publication and filing procedures could not vitiate the award.

p. 6

Legal principles established

#
  • Where parties by consent mark a suit as settled and refer emerging disputes to arbitration, the court is no longer seized of the dispute and the arbitration is governed by the Arbitration Act, not Order 45 of the Civil Procedure Rules.
  • The scope and extent of an arbitrator's mandate is fixed by contract between the parties, and a court cannot rewrite that mandate absent pleaded and proved coercion, fraud or undue influence.
  • In arbitration, jurisdiction is conferred by consent of the parties; a party who actively participates in arbitration after lapse of the agreed timeline, without intimating that time is of the essence, acquiesces in an extension and cannot later claim the award is a nullity.
  • Delay in delivering a judgment or ruling does not automatically vitiate it; the appellant must prove on a balance of probability that the delay occasioned a miscarriage of justice or erroneous findings of fact.

Court orders

#
  1. 1.The appeal is dismissed with costs
  2. 2.The cross-appeal is dismissed with costs

The bench

#

One judgment of the whole court — no separate or dissenting opinions.

majority
majority
majority
On appeal from
High Court of Kenya at Nairobi
Nairobi HCCC No. 200 of 2007
Jurisdiction invoked
Not expressly stated in the judgment; the appeal lay to the Court of Appeal from a ruling of the High Court dismissing an application to set aside an arbitral award.

Relief refused

#

Setting aside the arbitral award and remitting it to the arbitrator for reconsideration on quantum

The arbitration was consensual and conducted under the Arbitration Act; Order 45 was inapplicable; the arbitrator did not exceed his mandate; and the lapse of 120 days did not nullify the award given the parties' active participation

p. 7

Costs

Both the appeal and cross-appeal dismissed with costs.

Quotable passages

#

Verbatim from the judgment, each located to the page it appears on in the official PDF — so these can be cited and checked directly.

Accordingly, the final order of this Court is both the appeal and cross-appeal have no merit and are respectively hereby dismissed with costs.
p. 7Final orders and disposition
In light of this, we are satisfied the arbitration proceedings were not conducted pursuant to the provisions of the Civil Procedure Act and Rules. Consequently, we find Order 45 of the Civil Procedure Rules was inapplicable in this matter.
p. 5Governing framework of consensual arbitration
The scope and extent of mandate of an Arbitrator is an issue determined and fixed by contract between parties.
p. 5Arbitrator's mandate
In arbitration proceedings, jurisdiction is generally conferred by consent of the parties.
p. 6Consent as the source of arbitral jurisdiction
On the issue of joinder of Mr. Dhanji, estoppel by law operates against the appellant.
p. 5Estoppel from failure to appeal joinder
Bare allegations that the 14month delay is tantamount to an injustice does not suffice. The appellant should go further and prove on balance of probability the alleged injustice or misapprehension of facts occasioned by the delay.
p. 7Burden of proof on delay-based appeals

Issues in the judgment

#
minor

The judgment inconsistently renders the name of the case cited by the appellant as Kihuni vs. Gakunya, Kihuni vs. Gakunga and Kihuni vs. Gakunya (1986) eKLR, and the arbitration legislation referenced in Nyangau is cited as the Arbitration Act (cap 49) while the governing statute in this matter is the Arbitration Act No. 4 of 1995.

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Trishcon Construction Company Limited v Mohamed Salim Shamshudin & another [2019] KECA 821 (KLR)", Case Analysis (2019). Civil Appeal No. 28 of 2013. Source: https://new.kenyalaw.org/akn/ke/judgment/keca/2019/821/eng@2019-03-22

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.