Skip to content
AI-generated case briefs sourced from Kenya Law · Not legal advice
AI-generated case brief
Case Brief · caselaw.co.ke
Court of AppealDismissedCivil Appeal No. 33 of 2017· [2018] KECA 882 (KLR)

Sai Sports Limited v Narinder Singh Roopra, Surinder Singh Roopra, Kulwant Singh Roopra & Satnam Singh Roopra (trading as Motorways Construction)

Court of Appeal
19 January 2018
7,026 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~28 min to read original · ~4 min brief

The bottom line

#

Kenya's Court of Appeal dismissed Sai Sports' Kshs. 77 million construction claim because no completion date was ever written into the contract.

What this practically means

#

Executive summary

#
This is a first appeal from the High Court (Ochieng, J) which had awarded Sai Sports Limited only Kshs. 1,625,987.50 out of its claim of Kshs. 77,235,850.65 for breach of a partly oral, partly written building contract for a garments factory and directors' residence at a fixed price of Kshs. 26 million. The parties had jointly appointed a quantity surveyor, Mr. Mururu, whose binding report valued the works at Kshs. 19,807,001 and apportioned remedial costs equally. On appeal, the appellant contended the respondents breached representations, failed to complete by 31st August 1995, made unauthorised variations, and worked unprofessionally. A three-judge bench (Nambuye, Musinga and Gatembu Kairu, JJ.A) in a single judgment of the court dismissed the appeal. It held the trial Judge correctly found no completion date was agreed: the respondents' letter to the appellant's financier was to secure funding, not a contractual term, and delay was first raised only in November 1995. Absent an agreed date, completion within a reasonable time was implied. The finding that the appellant prevented work at the residence was supported by evidence, though breach of one part did not justify abandoning the whole. The Hedley Byrne claim failed for want of identified representations, and the special damages claims foundered on causation and remoteness, the appellant's own financial difficulties having contributed to the delay. The appeal was dismissed with costs to the respondents.

Key legal issues

#
01

Whether a completion date of 31st August 1995 was agreed

Holding

The trial Judge correctly rejected the claim that a completion date had been agreed; the letter to DFCK was to secure financing, not to fix a contractual term.

Reasoning

The contract was partly written and partly oral with no completion date in the respondents' bid, unlike other bidders who stated periods of 40-45 weeks. The 19th July 1995 letter was addressed to the appellant's financier, not the appellant, and was written long after work had commenced to facilitate release of funds. The delay complaint was first raised only in November 1995. The Judge's factual finding was amply supported and no basis for interference existed.

p. 9
02

Consequence of no agreed completion date

Holding

In the absence of an agreed date, an implied term of completion within reasonable time applies; the Judge rightly so held.

Reasoning

Citing Hudson's Building and Engineering Contracts and Hick v Raymond & Reid, the Court endorsed the implied obligation to complete within reasonable time where no date is fixed, with reasonableness assessed against the circumstances actually existing during performance. The respondents' liability could not extend to the actual completion date in 1999 by successors who took far longer and encountered additional works.

p. 9
03

Repudiation by eviction from site

Holding

The finding that the appellant prevented work at the residence was supported by the evidence; but breach as to the residence did not justify abandoning the factory works.

Reasoning

DW4 testified credibly that on 21st November 1995 the appellant's director stopped the workers at the residence. The Judge found this did not prevent work at the factory and that breach of one part did not entitle the respondents to treat the entire contract as breached. The Court declined to disturb this finding, noting no cross-appeal on severability.

p. 10
04

Hedley Byrne duty of care

Holding

The claim fails; no specific representations were identified and the appellant, having engaged an architect and spending Kshs. 26 million, could not be said to have wholly relied on the respondents.

Reasoning

Hedley Byrne liability requires a special relationship founded on a positive representation. Neither the pleadings nor evidence identified what representations the respondents made. Both parties bore blame for failing to engage professionals, as the joint expert also found, upholding the equal apportionment of remedial costs of Kshs. 4,865,977.

p. 10
05

Special damages heads of claim

Holding

The Judge adequately considered the principle underlying the claims; causation and remoteness under Hadley v Baxendale defeat them.

Reasoning

The claims for bank interest, rent, security, wages and professional fees were predicated on delay from a completion date never proved. The appellant's own financial difficulties contributed to the prolonged delay, and loan servicing was not shown to be pegged to completion as a contractual term. Losses outside the usual course and contemplation of the parties were irrecoverable.

p. 11

Legal principles established

#
  • The Court of Appeal as a first appellate court will not normally interfere with a trial court's findings of fact unless they are unsupported by evidence, based on a misapprehension of the evidence, or the trial court acted on a wrong principle.
  • Where a building contract specifies no completion date, an implied term to complete within a reasonable time applies, reasonableness being judged in the light of circumstances existing during performance.
  • A party's letter to a financier undertaking a completion date is not, without more, evidence of a term of contract between the contracting parties.
  • Liability for Hedley Byrne-type negligent misstatement requires proof of a positive representation or special relationship; it cannot rest on general reliance without identified representations.

Court orders

#
  1. 1.The appeal is dismissed
  2. 2.Costs of the appeal are awarded to the respondents

Authorities

#

Legislation

  • Court of Appeal RulesRule 29

Cases cited (10)

  • Hedley Byrne & Co. Ltd vs. Heller and Partners Ltd
    [1963] 2 All ER 593

    Duty of care in negligent statements causing financial loss where a special relationship exists.

  • Prudential Assurance Company of Kenya Limited vs. Sukhwinder Singh Jutley and another
    [2007] eKLR

    Completion date as an integral contract term; parol evidence cannot vary written terms.

  • Hadley vs. Baxendale
    (1854) 9 Exch. 341

    Causation and remoteness of damages for breach of contract.

  • Kinluc Holdings Ltd vs. Mint Holdings Ltd & another
    [1998] eKLR

    Loss from unauthorised unilateral variations to a contract to be borne by the varying party.

  • Cheall vs. Association of Professional Executive Clerical and Computer Staff
    [1983] 1 All ER 1134

    A party cannot rely on an event brought about by its own breach as terminating the contract.

  • Serah Njeri Mwobi vs. John Kimani Njoroge
    [2013] eKLR

    Estoppel/waiver of the right to challenge a report after refusing a joint inspection.

  • Independent Electoral & Boundaries Commission vs. Maina Kiai & 5 others
    [2017] eKLR

    Limits on the Court of Appeal's jurisdiction to interfere with lower court findings.

  • Charles Ogolla Obiero vs. Joseph Munyambu Karega
    [2017] eKLR

    Reaffirmation of the principles for interference with trial court findings of fact.

  • Selle and another versus Associated Motor Boat Company Limited & 2 others
    [1968] EA 123

    First appeal is by way of retrial; court re-evaluates evidence while making allowance for not seeing witnesses.

  • Hick vs. Raymond & Reid
    [1893] A.C. 22

    Reasonableness of completion time determined by circumstances existing during performance.

On appeal from
High Court of Kenya at Nairobi, Milimani Law Courts, Commercial & Admiralty Division
Commercial & Admiralty Division Case No. 2022 of 1996
Jurisdiction invoked
First appeal to the Court of Appeal under the Court of Appeal Rules (Rule 29 on the jurisdiction of the Court invoked by counsel); appeal from part of the High Court judgment and decree

Key timeline

#

Practical implications

#

Frequently asked questions

#

Later judgments citing this (2)

#

Judgments in the corpus that rely on this one. Where the Court said how it treated the authority, that is shown.

Cite this brief

#

Cite this brief

Caselaw, "Sai Sports Limited v Narinder Singh Roopra, Surinder Singh Roopra, Kulwant Singh Roopra & Satnam Singh Roopra (trading as Motorways Construction)", Case Analysis (2018). Civil Appeal No. 33 of 2017. Source: https://new.kenyalaw.org/akn/ke/judgment/keca/2018/882/eng@2018-01-19

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.