Court of AppealDismissedCivil Appeal 157 of 2006· [2012] KECA 43 (KLR)

SEVENTH DAY ADVENTIST CHURCH ) EAST AFRICA LTD & 2 OTHERS V MASOSA CONSTRUCTION COMPANY LIMITED [2012] KECA 43 (KLR)

Court of Appeal of Kenya
28 November 2012
1,765 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~7 min to read original · ~4 min brief

The bottom line

#

The Court of Appeal dismissed the SDA Church's appeal, holding it must pay the contractor the outstanding Shs.5.1 million because its own delayed payments caused the project's cost escalation.

What this practically means

#

Executive summary

#
Masosa Construction Company Limited sued the Seventh-day Adventist Church East Africa Ltd, its executive director Pastor R.M. Nyakego, and the project architect E.N. Aduke for Shs.5,177,688 being the unpaid balance of a contract to build a conference centre at the church's Nyamira church. The tender of Shs.17,102,152/20 was awarded in March 1995 for a 72-week construction period. Repeated stoppages, mainly from delayed payments by the church, extended the period to 176 weeks and escalated the cost to Shs.19,064,160. Wambilyangah, J., in H.C.C.C. No. 6 of 2002, delivered judgment on 15th September 2003 for Masosa for the unpaid balance with interest at court rates and costs. The appellants raised 11 grounds, principally that the pleadings departed from the evidence, that a written contract could not be varied orally, that the contract sum was Shs.10,600,000, that the 2nd appellant was wrongly held liable, and that the Judge erred on interest. The Court of Appeal, as first appellate court, re-evaluated the evidence and found the delay and cost escalation attributable to the church's failure to pay, the architect's failure to issue a final account, and a defence that was a mere denial. It upheld the trial Judge's findings of fact, held the 35% interest ground to be a non-issue since interest was awarded at court rates with no cross-appeal, and dismissed the appeal with costs to the respondent on 28th November 2012.

Key legal issues

#
01

Duty of the first appellate court

Holding

The Court of Appeal, as first appellate court, properly re-evaluated the evidence and agreed with the trial Judge's findings

Reasoning

The Court framed its task as re-evaluating the evidence before the High Court on both facts and law. It found the trial Judge had analysed the evidence extensively, noted the executive director's cross-examination admitting the church lacked funds, and concluded the delay and cost escalation fell squarely on the church. Findings of fact on credibility were upheld because there were no reasons to depart.

p. 3
02

Variation of the contract and escalation of the contract sum

Holding

The trial Judge was entitled to find the original written contract was varied by an oral agreement and by the lengthened performance period, raising the cost from Shs.17,102,152/20 to Shs.19,064,160

Reasoning

The extension from 72 to 176 weeks was mutual and arose from the church's failure to pay the contractor in time, causing cost escalation. The architect (3rd appellant) failed to produce a final account, and Masosa's quantity surveyor's itemised claim was never challenged. The trial Judge's quoted findings, including that the defence was a mere denial and the original contract was varied orally, were upheld as findings of fact.

p. 3
03

Interest at 35% per annum

Holding

The ground of appeal on interest failed because the trial Judge awarded interest at court rates, not 35% per annum, and there was no cross-appeal on interest

Reasoning

The appellants argued there was no agreement to pay interest at 35% per annum, but the Court observed the Judge never in fact allowed that rate, having awarded interest from the date of the plaint at court rates. Since there was no cross-appeal on the issue, the ground was a non-issue and could not succeed.

p. 4

Legal principles established

#
  • A first appellate court must re-evaluate the evidence before the trial court and ascertain whether the Judge reached the correct conclusion on both facts and law
  • An appellate court will not interfere with findings of fact of the trial court absent reasons to depart from them

Court orders

#
  1. 1.Appeal dismissed
  2. 2.Costs of the appeal awarded to the respondent
On appeal from
High Court of Kenya at Kisii
H.C.C.C. No. 6 of 2002
Jurisdiction invoked
First appellate jurisdiction over the High Court (duty to re-evaluate evidence, facts and law); no specific constitutional/statistical provision quoted in the judgment

Key timeline

#

Practical implications

#

Frequently asked questions

#

Later judgments citing this (1)

#

Judgments in the corpus that rely on this one. Where the Court said how it treated the authority, that is shown.

Cite this brief

#

Cite this brief

Caselaw, "SEVENTH DAY ADVENTIST CHURCH ) EAST AFRICA LTD & 2 OTHERS V MASOSA CONSTRUCTION COMPANY LIMITED [2012] KECA 43 (KLR)", Case Analysis (2012). Civil Appeal 157 of 2006. Source: https://new.kenyalaw.org/akn/ke/judgment/keca/2012/43/eng@2012-11-28

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.