Court of AppealPartially AllowedCivil Appeal No. 126 of 1998

OFFICIAL RECEIVER & INTERIM LIQUIDATORS CONTINENTAL CREDIT FINANCE LIMITED vs DETO INVESTMENT COMPANY LIMITED [1999] KECA 171 (KLR)

Court of Appeal of Kenya
22 October 1999
1,952 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~8 min to read original · ~4 min brief

The bottom line

#

Kenya's Court of Appeal cut a lender's damages bill to the interest its own delay caused, confirming lenders must promptly enforce repayment undertakings.

What this practically means

#

Executive summary

#
The respondent borrowed Kshs.1,275,000/= from the appellant in June 1982 to build five maisonettes, secured by an undertaking from Kenya National Assurance Co. Ltd (KNA) to repay the loan on demand, and a second loan of Kshs.217,000/= secured by a mortgage of 13th September 1983. The respondent alleged the appellant breached the offers of advance by failing to demand repayment from KNA in November 1983 when construction was completed, instead combining the loans, inflating the amount due, charging illegal penalties, and irregularly selling the maisonettes by public auction at an undervalue in April 1993. The High Court (Mwera J) found fraud not established and dismissed that limb, but entered judgment for the respondent on breach of contract and dismissed the appellant's counterclaim for Kshs.10,600,000/=. The Court of Appeal (Akiwumi, Tunoi and Owuor JJ.A) in a single judgment of the court held that the learned Judge did not err in entering judgment against the appellant, since the mortgage did not cover the first loan and KNA's unconditional undertaking was unaffected by unfulfilled pre-disbursement conditions. However, the court varied the quantum of general damages, holding that damages should be limited to the interest accumulated on the first loan (Kshs.3,993,975/60 as at June 1989) plus Kshs.1,000,000/= to the date of auction, totalling Kshs.4,993,975/60 with interest at court rates from 2nd April 1993. The appeal against dismissal of the counterclaim and the respondent's cross-appeal were both dismissed. Each party was ordered to bear its own costs. The decision binds subordinate courts on the measure of general damages for a lender's breach in failing to pursue a guarantor's undertaking.

Questions the Court framed

#

The issues the Court set itself to decide, in its own words.

  1. 1.Whether the learned Judge erred in entering judgment against the appellant (defendant below) on the respondent's claim for breach of contract
  2. 2.What was the correct quantum of general damages for breach of contract arising from the failure to demand repayment from KNA and the auction sale of the maisonettes
  3. 3.Whether the learned Judge erred in law in dismissing the appellant's counterclaim for the unpaid loan and interest
  4. 4.Whether the respondent's cross-appeal should succeed

Key legal issues

#
01

Liability of the appellant for breach of contract in failing to demand repayment from KNA

Holding

The learned Judge did not err in entering judgment against the appellant; the appellant's failure to demand repayment from KNA when it should have done so in November 1983, and its combination of the two loans, supported the finding of breach.

Reasoning

The respondent completed the maisonettes and by letter of 4th November 1983 requested the appellant to demand payment from KNA, which the appellant agreed to do but only did in 1989. The mortgage of 13th September 1983 did not cover the first loan of Kshs.1,275,000/= or interest thereon. KNA's unconditional undertaking was unaffected by the respondent's failure to fulfil pre-disbursement conditions, so the appellant's delay caused the accumulation of interest for which it was liable.

p. 3
02

Quantum of general damages for breach of contract

Holding

General damages should be limited to the accumulated interest on the first loan not recoverable under the mortgage, assessed at Kshs.3,993,975/60 as at 15th June 1989 plus Kshs.1,000,000/= to the date of the April 1993 auction, totalling Kshs.4,993,975/60 with interest at court rates from 2nd April 1993.

Reasoning

The auction sale was found not to have been fraudulent, so the special damages formula in the Further Amended Plaint (difference between market value and auction price) could not be transposed onto general damages. The proper measure was the interest that accumulated because the appellant failed to timeously demand repayment from KNA, with an additional sum to account for the period up to the auction.

p. 3
03

The appellant's counterclaim for the unpaid loan and interest

Holding

The appellant failed to establish its counterclaim and the appeal on that ground was dismissed.

Reasoning

On the court's analysis of the facts and law, the appellant could not sustain its claim for the balance of the unpaid loan and interest amounting to Kshs.10,600,000/=, given its own breach in failing to demand repayment from KNA and its treatment of the accounts.

p. 3
04

Fraud as pleaded by the respondent

Holding

Fraud was not established at trial and that aspect of the plaint was dismissed; the appeal court proceeded on the basis of breach of contract only.

Reasoning

The learned Judge found fraud had not at all been established and dismissed that limb, so no special or general damages for fraud were awarded. The court noted the distinction between fraud-based special damages and general damages for breach when assessing quantum.

p. 2

Legal principles established

#
  • Where a lender fails to demand repayment from a guarantor/insurer in accordance with its undertaking and instead combines loans and charges interest on the accumulated sum, the borrower's recoverable general damages are limited to the amount not recoverable under the mortgage, namely the accumulated interest on the loan that should have been repaid by the insurer.
  • General damages for breach of contract are not necessarily the same amount as special damages that would have been awarded had fraud been established, and must be assessed on the court's own view of the loss suffered.

Court orders

#
  1. 1.Judgment against the appellant upheld, but general damages reduced and substituted at Kshs.4,993,975/60 with interest thereon at court rates from 2nd April, 1993
  2. 2.The appellant's appeal on the dismissal of its counterclaim dismissed
  3. 3.The respondent's cross-appeal dismissed
  4. 4.Each party to bear its own costs

The bench

#

One judgment of the whole court — no separate or dissenting opinions.

majority
majority
majority
On appeal from
High Court of Kenya at Machakos
H.C.C.C. No. 100 of 1994
Jurisdiction invoked
First appeal to the Court of Appeal under the Kenyan appellate framework (specific provision not stated in the judgment)

Relief refused

#

Appellant's appeal against dismissal of its counterclaim for Kshs.10,600,000/=

The appellant did not establish its counterclaim on the facts and law

p. 3

Respondent's cross-appeal

The court's assessment of the law and facts did not support it

p. 3

Costs

Each party shall bear its own costs

Quotable passages

#

Verbatim from the judgment, each located to the page it appears on in the official PDF — so these can be cited and checked directly.

We do not think that the learned Judge erred in entering judgment against the appellant except that the damages awarded should have been Kshs.4,993,975/60 with interest thereon at court rates from 2nd April, 1993, and it is so ordered.
p. 3Final orders - variation of damages award
the amount of general damages should be based on the amount that was not recoverable under the mortgage namely, all the interest that had accumulated on the loan of Kshs.1,275,000/=
p. 3Measure of general damages for breach of contract by a lender
we conclude that the appellant did not establish its counterclaim and the appellant's appeal on the ground that the learned Judge erred in law in dismissing the appellant's counterclaim, is dismissed and it is so ordered.
p. 3Dismissal of counterclaim appeal
Having regard to the particular circumstances of this appeal and the cross appeal, each party shall bear its own costs.
p. 3Costs order

Issues in the judgment

#
minor

The judgment is dated and delivered on 22nd October 1999 but the header/coram context and the appeal number reference 1998; no internal contradiction in substance, noted only for completeness of the record.

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "OFFICIAL RECEIVER & INTERIM LIQUIDATORS CONTINENTAL CREDIT FINANCE LIMITED vs DETO INVESTMENT COMPANY LIMITED [1999] KECA 171 (KLR)", Case Analysis (1999). Civil Appeal No. 126 of 1998. Source: https://new.kenyalaw.org/akn/ke/judgment/keca/1999/171/eng@1999-10-22

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.